Months after construction began on the new train station at Miami International Airports transportation hub, state engineers realized they had a problem: The planned station platform was too short for some of the Amtrak trains that will use it. About 200 feet too short, in fact.
That meant some trains parked at the $88 million Miami Central Station would jut inconveniently out into the middle of Northwest 25th Street, one of just two direct connections for motorists between Northwest South River Drive and LeJeune Road east of the airport.
As it scrambles to correct the problem which is likely to cost several million dollars and could require permanently closing the street the Florida Department of Transportation is blaming Amtrak.
Agency engineers and consultants say the federal rail service failed to let the state agency know it would sometimes use longer trains on its Miami route than those the station was designed to accommodate. The FDOT says Amtrak raised no issues with platform length during extensive design-plan reviews that preceded the start of construction in May 2011.
An Amtrak spokeswoman said the agency had always warned FDOT that some of its trains could encroach into the street. But email exchanges released by FDOT suggest Amtrak first detailed the issue to an FDOT engineer in February 2012, nine months after the start of construction.
In any case, FDOT officials say, state taxpayers will now have to bear the cost of extending the platform all the way across 25th street, from the original length of 1,030 feet to 1,220 feet, or about a fifth of a mile. They are also exploring whether to build a bridge over the platform or sink the roadway below it, options which may prove unfeasible, or close the street permanently and look for other routes to get motorized traffic across the busy industrial area. That would likely require acquiring private property to carve out a new connecting street, FDOT said.
We just all wish they had made this known five years ago, said FDOT spokesman Ric Katz, adding that the state has no ability to get Amtrak to cover any of the cost. That said, we have to accommodate it.
FDOT plans to hold a public meeting some time in February for local business owners to discuss the alternatives. But agency officials say any permanent street solution wont be done until the end of 2014, or a year after the new rail station is scheduled to open.
Its not the best position to be in, but unfortunately were at this stage, said Carl Filer, FDOTs program manager for the Miami Intermodal Center, the MIA ground-transportation hub.
A price tag for the fixes is not yet available, but FDOT has set aside $3.7 million from its budget for the street reconfiguration. Contractors are now figuring the cost of extending the platforms, which have been redesigned and are already under construction. That expense would be covered by project contingency funds.
The train station, in the planning for 20 years, is part of the massive Miami Intermodal Center across LeJeune Road from the airport. Miami Central Station, linked to MIA via a People Mover, was designed to be the citys main passenger-rail hub, serving not just Amtraks national service but also regional Tri-Rail commuter trains. The train station is also connected to an adjacent new Metrorail station that serves the airport and the MICs giant car-rental facility.